Q3: Your company is planning to launch an important new project starting January 1, which will last one year. You estimate that you will need one full-time project manager, two full-time business analysts for the first six months, two full-time senior programmers for the whole year, four full-time junior programmers for the months of July, August, and September, and one full-time technical writer for the last three months. Use Microsoft Excel to create a stacked column chart showing a resource histogram for this project, similar to the one shown in Figure 9-6. Be soure to include a legend to label the types of resources needed. Use appropriate titles and axis labels. (Chapter 9, Exercise 1, page 380)